Energy projects, from site control to closeout.

Development, permitting, interconnection and construction run across months and many parties. Inspire Planner keeps every project, contractor and milestone in the Salesforce org where your deals and assets already live.

4.95/5 from 175+ reviews on AppExchange
Illustration: wind turbines and solar panels with a project schedule card
HOW PROJECTS RUN

Development through construction, in one plan

The stages most developers run each site through, from development to construction. Phases vary by region; the structure carries over.

  1. PHASE 1 Development Site control, feasibility and the commercial terms that make a project real.
  2. PHASE 2 Interconnection and permitting Applications, studies and permits, with long waits and hard dependencies.
  3. PHASE 3 Engineering and design Detailed design, permit sets and procurement.
  4. PHASE 4 Construction EPC and contractor work, inspections and key installs.
  5. PHASE 5 Closeout and handoff Commissioning, documentation and handoff to asset or account management.
PORTFOLIO BY PHASE

Every site, by phase, with its contractors

Development, permitting, construction and commissioning in one Portfolio Dashboard view. Contractors work in Inspire Planner - External Portal 2.0.

Diagram: renewable energy sites grouped by phase - development, permitting, construction and commissioning - each with its next milestone and the contractors working on it
Milestones that mean money Permit approval, interconnection agreement and key installs are milestones, so leadership sees what is holding up revenue.
Contractors in the plan EPC partners and contractors update their own tasks in External Portal instead of sending status by email.
Templates by region Permitting rules change by state or country, so teams keep a small set of templates per region and project size.
Illustrative example, not a customer plan. Patterns drawn from Inspire Planner onboarding and customer success work with teams in this industry.
IN INSPIRE PLANNER

Every site, milestone and contractor task in one plan

Development, permitting and construction run in the Project Gantt, next to the accounts and opportunities they belong to in Salesforce.

Project Gantt for Crestview Solar Farm - 80 MW: interconnection, environmental and permitting, engineering, construction and commissioning phases, with the county permit approval milestone.
A STARTING TEMPLATE

A development-to-construction template

A simplified structure many renewables teams start from. Real templates are tuned per region.

Who works in it
Development and project managers EPC partners and contractors, in External Portal PMO and executives, in the Portfolio Dashboard
WBSTASKTYPE
1 Development Phase
1.1 Site control and land agreements Task
1.2 Finalize construction (EPC) terms Task
2 Interconnection and permitting Phase
2.1 Interconnection application submitted Milestone
2.2 Site plan review Task
2.3 Permit submittal Milestone
2.4 Permit review and approval Task
3 Construction Phase
3.1 Mobilization Task
3.2 Modules installed Milestone
3.3 Inspections Checklist
4 Closeout and handoff Phase
4.1 Commissioning Milestone
4.2 Handoff to asset management Task
"We were able to quickly and easily translate deep process and project knowledge from our operations team into simple templating that has set us up for success as we move forward."
Sean Draper King Energy Rated 5 out of 5.   AppExchange review, Sep 2026

Questions from energy & renewables teams

Can contractors update tasks without a Salesforce license?

Yes. EPC partners and contractors use External Portal to see and update the tasks you share with them.

How do we handle different permitting rules by region?

Many teams keep a template per region and project type, and use Template Stitching or multi-template insert to combine common phases.

Can we see every project by stage?

Yes. The Portfolio Dashboard and Salesforce reports group projects by phase, region or owner.

Can milestones like permit approval show up for leadership?

Yes. Milestones roll up to the Portfolio Dashboard, so leadership sees what is holding each project.

Can we keep the detail without a 200-task plan?

Yes. Many teams move detail into checklists on key tasks, so the plan stays lean and reporting stays clear.